Jason
Aims
- Make progress on simulations in initial CS21p1 set
- Run Empirical Vertical models on a small/medium/large fault as an initial investigation
Highlights
- Underestimation of CS21.1 Core Hour Usage. Pushing us to 120% of our allocation on Kisti!
Completed
Issues
- CS some realisations have invalid VM perturbations, HF WCT underestimated significantly
- Poor Wall Clock Estimation tool. Will need to look at updating to Ethan's model with a modified Kisti factor before next large run.
- Poor WCT summary / breakdown / investigation tools.
- Ran out of time to run initial Empirical Vertical models.
- Will need to identify extra capacity for CS epic tasks
Outstanding
Initial Plan for next sprint
- Continue CS 21.1 execution on both initial set + issues and extended set [Execution]
- Expect to finish the initial set and make significant progress on extended set (initial allocation expires by the end of this sprint)
- Investigate what conclusions we can make about CH usage for CS21.1
- Run Empirical Vertical models [Execution]
- CS Plots / figure generation for CS paper as necessary
Other
[Anything else that doesn't fit in the other headings]