This is the a modification of of gmsim_v15v16.1.1 based on the work of Robin Lee in 2017/2018. Specifically:This version implements both modifications made in gmsim_v18.5.1 and gmsim_v18.5.2:

1. Removing the long period site amplification (or reducing to a 1-2s taper as opposed to the previous 2-5s taper?)

This change to reduce the long period site amplification was as a result of the CB14 site amplification overamplifying long periods since it double counts for velocity features which are already explicitly modelled in the LF simulations (due to the high resolution 3DVM).

 

2. Changing the HF path duration from Dp Dp = 0.07R to the Boore and Thomson (2014) path duration developed using the NGA-West2 database.databas

This change to increase the HF path duration was a result of the durations being identified as too short when compared to observed ground motions.

...